The Indian Contract Act, of 1872 uses the words penalty under section 74 as:
"Compensation of breach of contract where penalty stipulated for :- When a contract has been broken, if a sum is named in the contract as the amount be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss or proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for."
In section 74 the words that have to be emphasized upon are sum is named, penalty. The term sum is named gives out the meaning clearly that the amount that becomes payable in the event of any breach is pre estimated and is provided for in the contract. It is determined in the form of either damages or a stipulated penalty. Further, they sum that is so specified is the reasonable compensation for the breach and in no case the amount can be exceeded from what has been specified in the contract. Thus, in short section 74 talks about liquidated damages and not other kind of damages.
Liquidated damages: (not defined in the Indian Contract act, 1872)
If the sum fixed represents a genuine pre-estimate of the probable damages that is likely to result from the breach, it is liquidated damages.[1] An amount contractually stipulated as a reasonable estimate of actual damages to be recovered by one party if the other party breaches. It means that it shall be taken as the sum which the parties have by contract assessed as damages to be paid whatever maybe the actual damage.[2]
Penalty has been defined to mean 'I promise to pay so much of money if I break certain terms of the contract.'[5] It is 'a sum of money that is manifestly intended to be in excess of the amount which would fully compensate the other party for the loss sustained by him in consequence of the breach of the primary obligation.'[6]
On the other hand, the liquidated damages refer to genuine pre-estimate of losses and not a grand exemplification of the amount towards a specific breach.[11] However, it can be seen from the recent development of cases of Section 74 of the Indian Contract Act in the Supreme Court that these decisions are hampering the set peripheries of public and private law.[12]
One of the most talked about mechanisms of this act is the claim of compensation even though people are not able to prove, whether or not they suffered any actual severe loss. Kailash Nath case has critically subjected the issue to enable Damage or loss suffered as sine qua non for the applicability of Section 74.[13]
Section 74 becomes an inquisitive case for subjection to a study. The development of Section 74 through the cases of Maula Bux[14] Fateh Chand[15] and Saw pipes.[16] Section 74 has also been held in government contracts that the extent of damages for a breach of contract held for government agencies is based on the inconvenience caused to the public.
It is not because of the monetary loss that is suffered by the government agencies at that time.[17] It is important that the multinational giants are not given the free liberty to interpret section 74 as an advantageous position for them in Legal Battles.
This would prove to be very detrimental to the startups and new players in the market who would be bombarded with compensation of breach whether or not damages are occurred, or loss is suffered. Also, it is important that the clause specifies the difference between liquidated damages in the form of penalty and actual penalty clauses that mean pecuniary compensation.
The Legislative should also consider that provisions regarding liquidated damages which should come into play while dealing with government contracts. The provision of public inconvenience while dealing with liquidated damages should also be added in the Indian Contract Act 1872.
Gap in existing literature
Review of literature suggested that no study have been done in this legal dimension. There is a difference between the two as to the fact that penalty is limited to the extent to which the sum is stipulated in the contract and has been agreed by the parties although it is required to prove the fact that actual damages have accrued or not.
Whereas damages can be awarded by the court to the extent to which the innocent party has suffered a loss or as per the stipulation in the agreement without ascertaining the fact of the amount of loss that has actually occurred. The reason as to why damages and penalty are confused is mainly due to the liquidated damages which as per the Indian Contract Act have not been differentiated. This study will explain and make some practical ideas based on good legal principles to address the flaws in the "Concept of Penalty Under Indian Contract Law". No other study goes into immense detail about these ideas.
The author uses both primary as well as secondary sources. The secondary data is collected from published sources such as various books, Indian and foreign journals, online journals, newspapers, online newspapers, and research articles, and various websites on the subject to collect literature and data for the study and analysis.
Difference between Damages (not Liquidated Damages) and Penalty.
Penalty is the sanction for the breach of the parties imposed in the form of punishment whereas damages are an agreed sum of money that the parties consent to pay in the event of breach. Damages are reasonable compensation where as penalties are not.
Penalty is for enforcement of the obligation of performance on the said party whereas damages are to compensate the party which suffers a loss due to non performance of the said party.
This is the generic difference but "the distinction has been abolished in India. The courts award reasonable compensation not exceeding the stipulation. The courts knock down agreements which are unconscionable and extravagant."[26] "Section 74 is clearly an attempt to eliminate the somewhat elaborate refinements made under the English Common Law in distinguishing between stipulations providing for payment of the liquidated damages and stipulations in the nature of penalty. the Indian Legislation sought to cut across the web of rules and presumptions under the English Common Law by enacting a uniform principle applicable to all stipulations naming the amount to be paid in case of breach and stipulations by way of penalty."[27]
Current legislation governing penalty clauses regulation
The legislature in India has not stated the validity of penalty clauses. These clauses are governed under Chapter VI of the Indian Contract Act, 1872.
Section 73 of the Act states that compensation for loss is caused by breach of contract. It is defined as "When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach."
It is clear from this Section that the loss should be natural and should arise directly out of the breach of this contract. Further, this Section also discusses the remoteness of damage. Remoteness refers to whether the said damage was directly related to the breach. In cases where the damage is indirect and remote, the Court shall not give compensation to the defaulting party. Penalty clauses on the other hand are penal damages which are more than the loss which is incurred.
Section 74 of the Act defines Compensation for breach of Contract where penalty is stipulated for. Contracts in which there is a penalty clause, the aggrieved party can only ask for a reasonable compensation from the parties. The word reasonable is not stated but shall be taken up on a case-to-case basis looking at the circumstances of the case, the amount of default, paying capabilities of the parties etc.
Both liquidated damages and penalty follow the doctrine of reasonable compensation. Doctrine of Reasonable Compensation refers to when the compensation is "reasonable". Reasonability is determined by the facts and circumstances of each case. In case of a breaching party, reasonability may mean the damage suffered.
The Supreme Court of India in various judgements has mentioned the importance of reasonable compensation. In the case of Construction & Design Services v. Delhi Development Authority[28], the Court stated that the Court must determine the reasonable compensation and then grant it to the injured party.
Enforceability of a penalty clause
In India, the Validity of Penalty Clauses was questioned in various Supreme Court judgements. Generally, penalty clauses are taken in consideration with liquidated damages. In ONGC v. Saw Pipes[29], the Court laid down certain observations referring to Section 73 and 74 of the Act one of which was that "If the terms are clear and unambiguous stipulating the liquidated damages in case of the breach of the Contract unless it is held that such estimate of damages/compensation is unreasonable or is by way of penalty, the party who has committed the breach is required to pay such compensation and that is what is provided in Section 73 of the Contract Act."
The Law not only decides the amount of liquidated damages but also the compensation which is 'likely' to arise from the breach of the Contract[30].
Therefore, the Apex Court had explicitly stated that liquidated damages unless unreasonable or penalty shall be allowed. It further stated that even in case of unliquidated damages, if it is not unreasonable or penal then the Court shall allow compensation which is a genuine pre-estimate of the loss.
In Fateh Chand v. Balkishan Das[31], the Supreme Court similarly stated that the "Duty not to enforce the penalty clause but only to award reasonable compensation is statutorily imposed upon Courts by Section 74." Contracts with penalty clauses often are unreasonable and put burden on the defaulting party. Parties in case of wilful default might suffer consequences which are much more than their default. It can be said that putting unreasonable penalties on the defaulting party is against Public Policy.
In Central Inland Water Transport Corpn. Ltd. V. Brojo Nath Ganguly[32], the Supreme Court said that "Public Policy" and "Opposed to Public Policy" is not defined under the Indian Contract Act and is incapable of a precise definition. Therefore, what is injurious to public good can be the basic definition of 'Opposed to Public Policy'. Contracts with Penalty Clauses can be said to be against Public Policy because it is harmful to the parties who have defaulted even in cases when the default is not wilful.
Section 75 of the Indian Contract Act, 1872
According to this section, if a party rightfully rescinds a contract, then he can claim compensation for any losses or damages sustained due to non-performance of the contract.
Example: Peter is a drummer and enters into a contract with John, a nightclub owner. According to the contract, Peter agrees to play at John's club every Friday and Saturday night. The agreement is for the next two months against a payment of Rs 5,000 per night. On the fourth night, Peter wilfully absents himself from the club and John rescinds the contract. Since he does so rightfully, John can claim compensation for the damages sustained due to Peter's non-fulfillment of his promise.
Possible outcome and limitation of study
There is a difference between the two as to the fact that penalty is limited to the extent to which the sum is stipulated in the contract and has been agreed by the parties although it is required to prove the fact that actual damages have accrued or not. Whereas damages can be awarded by the court to the extent to which the innocent party has suffered a loss or as per the stipulation in the agreement without ascertaining the fact of the amount of loss that has actually occurred.
It can also exceed the amount that has been mentioned in the contract. Penalty whereas can't exceed or be claimed in excess of the sum that has been named in the contract between the parties. Penalty is awarded in case of breach and it is not in the form of compensation. "Damages are reasonable compensation whereas penalties are not." Thus, an aggrieved party should claim for damages which can put them in a better position in order to get the amount even for the mental trauma etc. that has been suffer by the innocent party due to breach.
In India, a variety of cases have been filed with reference to Liquidated Damages and Penalty. Only the amount which is reasonable to the breach shall be provided by the Courts. Therefore, the Indian judiciary makes penalty clauses valid only till the point where it is reasonable and not in excess of the breach.